ITIL 4 Foundation — Question 69
Which is a low risk change that has been pre-approved so that no additional authorization is needed?
Answer options
- A. A standard change
- B. A change model
- C. An emergency change
- D. A normal change
Correct answer: A
Explanation
A standard change is defined as a low risk change that has been pre-approved, allowing for implementation without needing additional authorization. In contrast, a change model refers to a structured approach for managing changes, while emergency and normal changes typically require more scrutiny and authorization due to their higher risk profiles.