ITIL 4 Foundation — Question 69

Which is a low risk change that has been pre-approved so that no additional authorization is needed?

Answer options

Correct answer: A

Explanation

A standard change is defined as a low risk change that has been pre-approved, allowing for implementation without needing additional authorization. In contrast, a change model refers to a structured approach for managing changes, while emergency and normal changes typically require more scrutiny and authorization due to their higher risk profiles.