ITIL 4 Foundation — Question 47
What is the PRIMARY use of a change schedule?
Answer options
- A. To support the 'incident management' practice and improvement planning
- B. To manage emergency changes
- C. To plan changes and help avoid conflicts
- D. To manage standard changes
Correct answer: C
Explanation
The primary function of a change schedule is to plan changes and help avoid conflicts, ensuring that changes can be implemented smoothly. While options A, B, and D relate to different aspects of change management, they do not directly address the main purpose of a change schedule.