Which is a key activity carried out in the 'did we get there?' step of the 'continual improvement' model?
Answer options
- A. Define measurable targets
- B. Perform baseline assessments
- C. Execute improvement actions
- D. Evaluate measurements and metrics
Correct answer: D
Explanation
The correct answer, D, refers to the evaluation of measurements and metrics, which is essential for determining if the improvement goals have been achieved. Options A, B, and C represent activities that occur at different stages of the improvement process, rather than during the assessment phase.