What is a change schedule PRIMARILY used for?
Answer options
- A. To help plan emergency changes
- B. To help authorize standard changes
- C. To help assign a change authority
- D. To help manage normal changes
Correct answer: D
Explanation
The correct answer is D because a change schedule is primarily used to manage and track normal changes within an organization. Options A, B, and C refer to specific functions that may relate to changes but do not capture the primary role of a change schedule.