ITIL 4 Foundation — Question 26
Which practice is responsible for moving new or changed components to live or other environments?
Answer options
- A. Release management
- B. Deployment management
- C. Change enablement
- D. Supplier management
Correct answer: B
Explanation
The correct answer is B, Deployment management, as it specifically focuses on the process of moving and installing new or updated components into live environments. A, Release management, is more about the planning and scheduling of releases, while C, Change enablement, handles the broader aspects of managing changes, and D, Supplier management, deals with vendor relationships rather than deployment processes.