ITIL 4 Foundation — Question 26

Which practice is responsible for moving new or changed components to live or other environments?

Answer options

Correct answer: B

Explanation

The correct answer is B, Deployment management, as it specifically focuses on the process of moving and installing new or updated components into live environments. A, Release management, is more about the planning and scheduling of releases, while C, Change enablement, handles the broader aspects of managing changes, and D, Supplier management, deals with vendor relationships rather than deployment processes.