EXIN ITIL Foundation — Question 6

What is the name of the group that should review changes that must be implemented faster than the normal change process?

Answer options

Correct answer: B

Explanation

The Emergency change advisory board is specifically designated to evaluate and approve changes that require expedited processing. The other options, while related to change management, do not focus on the urgent nature of these modifications, making them unsuitable for this context.