Scrum Master Certified (SMC) — Question 45

Which one of the following is NOT a type of identified dependencies in a Scrum project?

Answer options

Correct answer: A

Explanation

The correct answer is A, as 'Critical' is not recognized as a type of dependency in Scrum. The other options—Mandatory, Discretionary, and Internal—are valid categories that describe different kinds of dependencies that can arise in a project.