Scrum Master Certified (SMC) — Question 45
Which one of the following is NOT a type of identified dependencies in a Scrum project?
Answer options
- A. Critical
- B. Mandatory
- C. Discretionary
- D. Internal
Correct answer: A
Explanation
The correct answer is A, as 'Critical' is not recognized as a type of dependency in Scrum. The other options—Mandatory, Discretionary, and Internal—are valid categories that describe different kinds of dependencies that can arise in a project.