Scrum Master Certified (SMC) — Question 44

Between traditional Project Management and Scrum, differences exist in how quality is achieved and/or implemented. In this respect, which of the following is NOT true?

Answer options

Correct answer: C

Explanation

The correct answer is C because, in Scrum, the Scrum Master facilitates the process, but it is the entire Scrum Team that collaborates to define the Acceptance Criteria. Options A and B accurately describe traditional project management, while D correctly explains the iterative nature of Scrum through Sprints.