Scrum Master Certified (SMC) — Question 46

One of the responsibilities of the Scrum Master is to facilitate timely identification of all risks faced by the Scrum Team. As the Scrum Master for a team working on a banking application project, which of the following techniques would you suggest for comprehensive risk identification?

Answer options

Correct answer: B

Explanation

The Probability Impact Grid is effective for evaluating risks based on their likelihood and potential impact, making it a comprehensive tool for risk identification. While Risk Appetite, Risk Checklists, and Risk Meetings are useful methods, they do not provide the same structured approach to prioritize risks based on their significance.