Scrum Master Certified (SMC) — Question 22

The Chief Scrum Master plays an important role during the Retrospect Project process. By being a part of the Retrospect Project Meeting, he/she provides valuable inputs mainly to identify, document, and internalize the lessons learned during the process. What is an output of this process?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the Retrospect Project process aims to identify actionable improvements that can be implemented in future projects. Options B, C, and D do not specifically refer to the improvements derived from lessons learned, making them incorrect in this context.