Scrum Master Certified (SMC) — Question 23
While assisting the Product Owner in developing a Prioritized Product Backlog, the Scrum Master must consider the primary factors on which the Prioritized
Product Backlog is based-on. Which of the following are those primary factors?
A) Value -
B) Dependencies -
C) Risk -
D) Deliverables -
Answer options
- A. A, В, and С
- B. A
- C. A, C, and D
- D. С
Correct answer: A
Explanation
The correct answer is A because the primary factors for a Prioritized Product Backlog include Value, Dependencies, and Risk, which are crucial for making informed prioritization decisions. Option B is incomplete as it only considers Value, while options C and D do not include all necessary factors.