ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 160
Can an it_project_manager convert a task to a milestone?
Answer options
- A. Yes, if the task is assigned to the project manager.
- B. Yes, by right-clicking on the task in the Planning Console.
- C. No, the PPS admin role is also required.
- D. No, this can only be done by a system admin.
Correct answer: B
Explanation
The correct answer is B because the Planning Console allows users to right-click on tasks to convert them into milestones. Option A is incorrect because the assignment of the task to the project manager does not grant the authority to make this change. Options C and D are also wrong as they imply that a higher-level role is necessary, which is not the case in this specific context.