ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 160

Can an it_project_manager convert a task to a milestone?

Answer options

Correct answer: B

Explanation

The correct answer is B because the Planning Console allows users to right-click on tasks to convert them into milestones. Option A is incorrect because the assignment of the task to the project manager does not grant the authority to make this change. Options C and D are also wrong as they imply that a higher-level role is necessary, which is not the case in this specific context.