ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 159

How can the planned start date on a WIP/Closed task be changed?

Answer options

Correct answer: C

Explanation

The correct answer is C, as it specifically allows for changing planned dates on tasks that are in WIP or Closed status. Options A and B do not pertain to the WIP/Closed status and focus on different aspects of project management. Option D relates to cost aggregation, which is not relevant to changing task dates.