ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 159
How can the planned start date on a WIP/Closed task be changed?
Answer options
- A. By setting the property – 'Enable firing of Business Rules on save from Planning Console'
- B. By setting the property – 'Enable alter of planned date with Actual for Manual Project'
- C. By setting the property – 'Enable altering of planned date(s) for task in WIP/Closed'
- D. By setting the property – 'Enable project cost rollup'
Correct answer: C
Explanation
The correct answer is C, as it specifically allows for changing planned dates on tasks that are in WIP or Closed status. Options A and B do not pertain to the WIP/Closed status and focus on different aspects of project management. Option D relates to cost aggregation, which is not relevant to changing task dates.