ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 158

The Project Management application enables users to create parent-child relationships between tasks and dependencies, such as finish-to-start and finish-to-finish, between tasks. How many relationships can exist between two tasks?

Answer options

Correct answer: A

Explanation

The correct answer is A, as there can only be one relationship type defined between any two tasks in the Project Management application. Options B, C, and D suggest multiple relationships, which is not supported by the application's design.