ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 103

Actuals on a resource plan are updated by what activity?

Answer options

Correct answer: D

Explanation

The correct answer is D because actuals are updated in the resource plan once the time card is approved, confirming that the reported hours are accurate. Options A and B involve submitting and entering data, respectively, but they do not complete the validation process necessary for updating actuals. Option C refers to the approval of the resource plan itself, which does not directly impact the update of actuals.