ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 103
Actuals on a resource plan are updated by what activity?
Answer options
- A. User submits time card
- B. Project manager enters actuals
- C. Resource plan is approved
- D. Time card is approved
Correct answer: D
Explanation
The correct answer is D because actuals are updated in the resource plan once the time card is approved, confirming that the reported hours are accurate. Options A and B involve submitting and entering data, respectively, but they do not complete the validation process necessary for updating actuals. Option C refers to the approval of the resource plan itself, which does not directly impact the update of actuals.