What must a resource plan contain if a resource plan is associated with a time card?
Answer options
- A. Soft allocation bookings.
- B. Front load allocation spread.
- C. Hard allocation bookings.
- D. Even allocation spread.
Correct answer: C
Explanation
A resource plan associated with a time card must include hard allocation bookings to ensure that resources are definitively assigned and accounted for. The other options, such as soft allocation bookings and different types of spreads, do not guarantee the same level of commitment to resource allocation.