ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 104

If a resource plan is not associated manually to a time card, then a resource plan is auto-associated. The auto-association is done based on which of the following in the time card?

Answer options

Correct answer: A

Explanation

The correct answer is 'task' because the system uses the tasks on the time card to determine which resource plan should be automatically associated. The other options, such as 'hard allocation' and 'soft allocation', refer to different methods of resource management but do not play a role in the auto-association process.