In the baseline Change - Normal model how can Change Tasks be added? (Choose two.)

Answer options

Correct answer: A, D

Explanation

Option A is correct because Change Tasks can indeed be added automatically through the Change - Implementation subflow. Option D is also correct as users can manually add Change Tasks during all states except when the change is Closed or Canceled. Options B and C are incorrect because they either limit the states or do not accurately reflect the automatic addition of tasks.