Professional Scrum Product Owner I (PSPO I) — Question 15
Which is NOT a valid consideration when ordering a Product Backlog? (Choose the best answer.)
Answer options
- A. Importance to customers.
- B. Tools and techniques.
- C. Alignment with business strategy and goals.
- D. Risk.
- E. Dependencies on other Product Backlog items.
Correct answer: B
Explanation
The correct answer is B, as tools and techniques are not typically used to prioritize items in the Product Backlog. Instead, considerations like customer importance, alignment with business goals, risk, and dependencies are crucial for effective backlog management.