Professional Scrum Product Owner I (PSPO I) — Question 14
Why does the Product Owner want the Developers to adhere to its Definition of Done? (Choose the best answer.)
Answer options
- A. To be able to reprimand the team when they do not meet their velocity goal for the Sprint.
- B. To predict the team's productivity over time.
- C. To have complete transparency into what has been done at the end of each Sprint.
- D. To know what the team will deliver over the next three Sprints.
Correct answer: C
Explanation
The correct answer is C because adhering to the Definition of Done ensures that all completed work meets a clear standard, allowing the Product Owner to clearly see what has been accomplished at the end of each Sprint. The other options, while related to team performance and planning, do not directly address the need for transparency regarding completed work.