Professional Scrum Product Owner I (PSPO I) — Question 13

Which of the following are criteria to order Product Backlog items? (Choose all that apply.)

Answer options

Correct answer: A, B, C

Explanation

The correct criteria for ordering Product Backlog items include the value of the items, any dependencies between those items, and dependencies with other products. The availability of the Scrum Master is not a relevant factor for prioritization.