Professional Scrum Product Owner I (PSPO I) — Question 16

In the middle of the Sprint, the customer decides that there are two new features she wants. The Product Owner could: (Choose two.)

Answer options

Correct answer: B, D

Explanation

The correct actions are to add the features to the Product Backlog (B) for future prioritization and to have the Developers assess the feasibility of adding them without compromising the Sprint Goal (D). Options A and C are incorrect because introducing new work in the middle of a Sprint without proper backlog management is against Scrum principles.