Professional Scrum Master II (PSM II) — Question 98

What is the most appropriate action for the Scrum Master to take if the Product Owner is having difficulties managing the Product Backlog?

Answer options

Correct answer: C

Explanation

The correct answer is C because it emphasizes the Scrum Master's role in supporting the Product Owner to enhance their understanding and effectiveness in managing the Product Backlog. Options A, B, D, and E are incorrect as they either undermine the Product Owner's role, misallocate responsibilities, or suggest unnecessary delays in the Sprint process.