Professional Scrum Master II (PSM II) — Question 97
A Scrum Master teaches those who are interested in the Development Team's progress that progress in Scrum comes from inspecting an Increment at the Sprint
Review.
Answer options
- A. True
- B. False
Correct answer: A
Explanation
The correct answer is True because the Sprint Review is a key event in Scrum where the team inspects the Increment and discusses progress. The statement is accurate, while the option False is incorrect as it contradicts Scrum principles regarding the importance of the Sprint Review.