Professional Scrum Master II (PSM II) — Question 99
What action should a Scrum Master take if the Development Team has decided that Retrospectives are no longer necessary?
Answer options
- A. Start facilitating more productive and useful Retrospectives.
- B. Suggest reducing the frequency of the Retrospectives.
- C. Extend the Sprint time-box in order to fit the Retrospectives.
- D. Comply with the team's decision.
Correct answer: A
Explanation
The correct answer is A because the Scrum Master is responsible for ensuring that the Scrum process is followed and that the team continuously improves, which includes facilitating Retrospectives. The other options either diminish the importance of Retrospectives or comply with a decision that may hinder team growth.