How should a Scrum Master coordinate the work when more than one Scrum Team is working on one product?

Answer options

Correct answer: A

Explanation

The correct answer, A, emphasizes the Scrum Master's role in guiding teams to take responsibility for inter-team coordination, ensuring a cohesive product Increment. Options B and C, while relevant, do not directly address the Scrum Master's responsibility in facilitating collaboration. Option D is not practical as merging teams can introduce complexity and disrupt established workflows.