Professional Scrum Master II (PSM II) — Question 92
If there are multiple Scrum Teams working on the same product, all of the Scrum Teams must mutually define a Definition of Ready (DoR). The DoR is a checklist that the Product Owner must fulfill before a Product Backlog item can be presented at the Sprint Planning. This protects the Development Team from interruptions and disruptions during the Sprint.
Answer options
- A. True
- B. False
Correct answer: B
Explanation
The correct answer is B because while Scrum Teams may have the option to define a Definition of Ready together, it is not mandatory for all teams to do so. Each Scrum Team can establish its own DoR based on their specific needs, and thus collaboration on a single DoR is not a requirement.