Professional Scrum Master II (PSM II) — Question 94

What would be typical Scrum Master activities during the Sprint?

Answer options

Correct answer: B

Explanation

The correct answer is B because a Scrum Master's role includes removing impediments and facilitating necessary discussions for continuous improvement. Option A misrepresents the Scrum Master’s role by suggesting they assign tasks, which is the responsibility of the Development Team. Option C incorrectly suggests that the Scrum Master should avoid conflicts rather than address and resolve them.