Professional Scrum Master II (PSM II) — Question 94
What would be typical Scrum Master activities during the Sprint?
Answer options
- A. Monitor the progress of the Development Team and assigning tasks.
- B. Remove impediments and facilitating inspection and adaptation opportunities as requested or needed.
- C. Avoiding conflicts and escalating to the line managers if conflicts occur.
Correct answer: B
Explanation
The correct answer is B because a Scrum Master's role includes removing impediments and facilitating necessary discussions for continuous improvement. Option A misrepresents the Scrum Master’s role by suggesting they assign tasks, which is the responsibility of the Development Team. Option C incorrectly suggests that the Scrum Master should avoid conflicts rather than address and resolve them.