A Development Team member has notified the Scrum Master of a potential data security risk.
What action should the Scrum Master take?
Answer options
- A. Notify the test team.
- B. Add a Product Backlog item to address the security issue.
- C. Ask the Development Team member to share the issue with the team as soon as possible.
- D. Wait until the Sprint Retrospective to add security to the definition of ג€Doneג€.
Correct answer: C
Explanation
The correct answer is C because the Scrum Master should encourage prompt communication among team members regarding potential risks. Options A and B are not immediate responses to the issue, and option D delays addressing the security concern, which could lead to vulnerabilities.