Professional Scrum Master II (PSM II) — Question 77

Which of the following statements are true about the Scrum Master role?

Answer options

Correct answer: B

Explanation

Option B is correct because the Scrum Master facilitates communication and ensures that the Development Team adheres to the time constraints of Scrum meetings. Option A is incorrect as the Scrum Master does not assign tasks; this is the role of the Development Team. Option C is not accurate since updating the Scrum board is typically a responsibility of the Development Team, and managing conflicts is a shared responsibility within the team. Option D is also incorrect as the Development Team is primarily responsible for demonstrating the Increment, not the Scrum Master.