Professional Scrum Master II (PSM II) — Question 79
A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments.
Which would be the LEAST helpful technique in this situation?
Answer options
- A. Consulting with the Development Team
- B. Prioritizing the list and working on them in order.
- C. Arranging a triage meeting with all project managers.
- D. Alerting management to the impediments and their impact.
Correct answer: C
Explanation
The correct answer is C because arranging a triage meeting with all project managers may not directly address the impediments faced by the Scrum Team and could lead to further delays. In contrast, consulting with the Development Team, prioritizing the impediments, and alerting management can lead to more immediate and actionable resolutions.