Professional Scrum Master II (PSM II) — Question 50

At the Sprint Planning, the Development Team is not able to forecast the number of Product Backlog items it can do in the upcoming Sprint due to unclear requirements. The Product Owner, however, was able to clearly define the business objective he hopes to achieve in the Sprint.
Which of the following two actions would you support? (Choose two.)

Answer options

Correct answer: A, D

Explanation

Option A is correct as it suggests a proactive approach by the Development Team to forecast and start implementation based on a likely design, allowing them to refine their work during the Sprint. Option D is also correct as it focuses on reflecting and learning from the situation in the Sprint Retrospective, which is essential for continuous improvement. Options B and C are not ideal because extending the Sprint Planning time or allowing indefinite review can hinder the Scrum process and delay progress.