Professional Scrum Master II (PSM II) — Question 49

Steven is a Scrum Master of a Scrum Team that is new to Scrum. At the halfway point of the Sprint, the Product Owner comes to Steven telling him that he is concerned the Development Team will not be able to complete the entire Sprint Backlog by the end of the Sprint.
What should Steven do in this situation?

Answer options

Correct answer: B

Explanation

The correct answer is B because it emphasizes the nature of complex software development, where unforeseen work can emerge, affecting the initial scope. Options A and D are incorrect as they either pressure the team or suggest adding resources, which does not address the underlying issue. Option C misrepresents the Scrum framework, as the Product Owner and Development Team should collaborate on the Sprint Backlog.