Steven is a Scrum Master of a Development Team that has members working in different cities and time zones. Organizing the Scrum events is time consuming and requires a lot of effort to set up and run. The Development Team proposes to only hold the Daily Scrum on Mondays.
Which two responses would be most appropriate from Steven? (Choose two.)

Answer options

Correct answer: A, C

Explanation

The correct responses are A and C because they emphasize the importance of regular communication and collaboration in Scrum, which is essential for achieving the Sprint Goal and maintaining team cohesion. Option B is not appropriate as voting goes against the collaborative nature of Scrum, and option D fails to address the potential negative impacts of reducing the frequency of Daily Scrums.