Professional Scrum Master II (PSM II) — Question 51

Steven is a Scrum Master on a new Scrum Team.
What would be the best way for him to determine if the Product Owner is interacting enough with the Development Team during a Sprint?

Answer options

Correct answer: B

Explanation

The correct answer is B because the effectiveness of the Product Owner's engagement can be gauged by whether the Increment aligns with their expectations, indicating successful collaboration. The other options focus on participation in events or incorrect assumptions about presence, which do not directly reflect the overall interaction and collaboration during the Sprint.