Professional Scrum Master II (PSM II) — Question 185
When scaling Scrum it is important to have multiple Scrum Teams working from one Product Backlog.
Answer options
- A. True
- B. False
Correct answer: A
Explanation
The correct answer is True because multiple Scrum Teams can effectively collaborate and align their efforts towards a common goal when they all refer to the same Product Backlog. This alignment helps to maintain consistency in priorities and facilitates better communication among teams. Answer B is incorrect as having separate Backlogs could lead to misalignment and fragmentation of work.