Professional Scrum Master II (PSM II) — Question 186
What is one way to determine if the Product Owner is interacting with the Developers enough throughout a Sprint?
Answer options
- A. Product Owners and Developers are satisfied with the increment.
- B. Check the Daily Scrum reports to see whether the Product Owner was present at the majority of the Daily Scrum meetings.
- C. The Developers should determine the percentage of time the Product Owner is required to be present and monitor whether the Product Owner's average presence is around this figure.
- D. Observe whether the Developers need to ask the Product Owner questions at times other than during the Daily Scrum.
Correct answer: D
Explanation
The correct answer, D, indicates that if Developers frequently need to ask questions outside of the Daily Scrum, it suggests that the Product Owner is not adequately available. Options A, B, and C do not directly measure the interaction level but rather assess satisfaction or attendance without focusing on the necessity for communication outside established meetings.