Professional Scrum Master II (PSM II) — Question 143

Part of the team's Definition of `Done` requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?

Answer options

Correct answer: B

Explanation

The correct answer is B because the Development Team is responsible for all aspects of the Increment, including documentation, even in the absence of the technical writer. Answer A suggests forming a new team, which may not be feasible or efficient. Option C delays necessary work, and D can lead to incomplete documentation, violating the Definition of `Done`.