Professional Scrum Master II (PSM II) — Question 144
Kevin is a senior developer that has recently joined an existing Scrum Team. The existing team members are unable to get along with Kevin and conclude that he is not a culture fit.
If necessary, who is responsible for removing the new team member, and why?
Answer options
- A. The Scrum Master because he/she is responsible for removing Impediments.
- B. The Development Team is responsible because it is an internal team issue, and may request help from the Scrum Master.
- C. The HR department, as they are responsible for the hiring process.
- D. The Product Owner because he/she is responsible for managing the team.
Correct answer: B
Explanation
The correct answer is B because the Development Team is responsible for its internal dynamics and can decide to address issues among themselves. While the Scrum Master may help facilitate the process, it is ultimately the team's decision on how to handle conflicts or remove a member. Options A, C, and D are incorrect as they do not place the responsibility on the Development Team, which is essential in a Scrum framework.