The Product Backlog is ordered by:
Answer options
- A. The Product Owner with the most valuable items placed at the top.
- B. Risk, where safer items are at the top, and riskier items are at the bottom.
- C. Items are randomly arranged.
- D. Size, where small items are at the top and large items are at the bottom.
Correct answer: A
Explanation
The correct answer is A because the Product Owner is tasked with prioritizing the Product Backlog based on the value of items. Option B incorrectly suggests that risk determines the order, while C states that items are arranged randomly, which is not the case. Option D incorrectly implies that size is the criteria for ordering, not value.