Professional Scrum Master I (PSM I) — Question 80
What is the timebox for the Sprint Review?
Answer options
- A. As long as needed.
- B. 2 hours for a one-month Sprint.
- C. 4 hours for a one-month Sprint.
- D. 1 day
Correct answer: C
Explanation
The correct answer is C, as the Scrum Guide specifies that the Sprint Review should be timeboxed to a maximum of 4 hours for a one-month Sprint. Options A and D are incorrect because they do not adhere to the specified time limits, and option B is incorrect because it underestimates the timebox for a one-month Sprint.