Professional Scrum Master I (PSM I) — Question 82
What are two effective ways for the Scrum Team to make non-functional requirements visible? (Choose two.)
Answer options
- A. Put them on a separate list on the Scrum board, available for all to see.
- B. Add them to the Product Backlog to ensure transparency.
- C. Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.
- D. Add them to the definition of ג€Doneג€ so the work is taken care of every Sprint.
Correct answer: B, D
Explanation
The correct answers, B and D, ensure that non-functional requirements are consistently monitored and met. Adding them to the Product Backlog (B) allows for ongoing visibility and prioritization, while including them in the definition of 'Done' (D) guarantees they are part of the completion criteria for each Sprint. Options A and C do not provide the same level of integration and ongoing attention to non-functional requirements as B and D do.