Professional Scrum Master I (PSM I) — Question 82

What are two effective ways for the Scrum Team to make non-functional requirements visible? (Choose two.)

Answer options

Correct answer: B, D

Explanation

The correct answers, B and D, ensure that non-functional requirements are consistently monitored and met. Adding them to the Product Backlog (B) allows for ongoing visibility and prioritization, while including them in the definition of 'Done' (D) guarantees they are part of the completion criteria for each Sprint. Options A and C do not provide the same level of integration and ongoing attention to non-functional requirements as B and D do.