Professional Scrum Master I (PSM I) — Question 77
What factor should be considered when establishing the Sprint length?
Answer options
- A. The frequency at which team formation can be changed.
- B. The organization has mandated similar length sprints.
- C. The organization's release schedule.
- D. The need for the team to learn based on doing work and measuring results.
Correct answer: D
Explanation
The correct answer is D because the length of the Sprint should allow the team to gain insights through practical experience and evaluating outcomes. Options A, B, and C do not focus on the learning aspect that is crucial for the team's development and adaptation during the Sprint process.