Professional Scrum Master I (PSM I) — Question 76
An Increment must be released to customers or users at the end of each Sprint.
Answer options
- A. True
- B. False
Correct answer: B
Explanation
The correct answer is B because while it is encouraged to release an Increment at the end of each Sprint, it is not mandatory. The decision to release depends on various factors such as the readiness of the product and stakeholder input, making A an incorrect choice.