Professional Scrum Master I (PSM I) — Question 76

An Increment must be released to customers or users at the end of each Sprint.

Answer options

Correct answer: B

Explanation

The correct answer is B because while it is encouraged to release an Increment at the end of each Sprint, it is not mandatory. The decision to release depends on various factors such as the readiness of the product and stakeholder input, making A an incorrect choice.