Professional Scrum Master I (PSM I) — Question 78
When must a Scrum Team release each Increment?
Answer options
- A. When it makes sense to release it.
- B. When the Scrum Team finishes their work.
- C. Whenever the product is free of defects.
- D. After every Sprint, without exception.
Correct answer: A
Explanation
The correct answer is A, as releasing an Increment should be based on the value it provides rather than arbitrary deadlines or completion of tasks. Options B and D imply a rigid timeline for releases, while C focuses too much on defects, which does not consider the overall value and timing of the release.