Professional Scrum Master I (PSM I) — Question 72
When do Development Team members take ownership of a Sprint Backlog item? (Choose the best answer.)
Answer options
- A. At the Sprint planning meeting.
- B. During the Daily Scrum.
- C. Never. All Sprint Backlog Items are ג€ownedג€ by the entire Scrum Team.
- D. Whenever a team member can accommodate more work.
Correct answer: C
Explanation
The correct answer is C because in Scrum, all Sprint Backlog items are collectively owned by the Scrum Team, emphasizing collaboration. Options A, B, and D suggest individual ownership or specific instances, which contradict the principle of shared accountability in Scrum.