Professional Scrum Master I (PSM I) — Question 72

When do Development Team members take ownership of a Sprint Backlog item? (Choose the best answer.)

Answer options

Correct answer: C

Explanation

The correct answer is C because in Scrum, all Sprint Backlog items are collectively owned by the Scrum Team, emphasizing collaboration. Options A, B, and D suggest individual ownership or specific instances, which contradict the principle of shared accountability in Scrum.