Professional Scrum Master I (PSM I) — Question 71
The Product Owner determines how many Product Backlog items the Development Team selects for a Sprint.
Answer options
- A. False.
- B. True, accordingly to what was committed to the stakeholders.
- C. True, but only after confirmation by the resource manager that the Team has enough capacity.
- D. True.
- E. False, the Scrum Master does that.
- F. False, capacity and commitment are the Project manager's responsibility.
Correct answer: A
Explanation
The correct answer is A because the Development Team itself decides how many items to take into the Sprint during Sprint Planning, not the Product Owner. Options B, C, D, E, and F incorrectly attribute the decision-making power to the Product Owner, Scrum Master, or Project Manager, which is not how Scrum operates.