Professional Scrum Master I (PSM I) — Question 71

The Product Owner determines how many Product Backlog items the Development Team selects for a Sprint.

Answer options

Correct answer: A

Explanation

The correct answer is A because the Development Team itself decides how many items to take into the Sprint during Sprint Planning, not the Product Owner. Options B, C, D, E, and F incorrectly attribute the decision-making power to the Product Owner, Scrum Master, or Project Manager, which is not how Scrum operates.