Professional Scrum Master I (PSM I) — Question 73
Who creates the definition of `Done`?
Answer options
- A. The Scrum Master as he/she is responsible for the Development Team's productivity.
- B. The Scrum Team, in a collaborative effort where the result is the common denominator of all members' definition.
- C. The Product Owner as he/she is responsible for the product's success.
- D. The development organization (or Development Team if none is available from the development organization).
Correct answer: B
Explanation
The correct answer is B because the definition of `Done` is established collaboratively by the Scrum Team to ensure everyone has a shared understanding. Option A is incorrect as the Scrum Master facilitates but does not solely create it, C is wrong since the Product Owner focuses on product success rather than team definitions, and D is misleading because it implies a broader organizational role rather than the collaborative team effort required in Scrum.