Professional Scrum Master I (PSM I) — Question 62
When is it most appropriate for a Scrum Team to change the Definition of Done?
Answer options
- A. Prior to starting a new project.
- B. During Product Backlog refinement.
- C. During Sprint Planning.
- D. During the Sprint Retrospective.
Correct answer: D
Explanation
The correct answer is D, as the Sprint Retrospective is a time for the Scrum Team to reflect on their process and make adjustments, including the Definition of Done. Options A, B, and C do not provide the same opportunity for reflection and improvement, making them less suitable for such changes.