Professional Scrum Master I (PSM I) — Question 63

A new Developer is having continuing conflicts with existing members of the Scrum Team, which is impacting the delivery of the Increment. If necessary, who is responsible for removing the Developer from the Scrum Team?

Answer options

Correct answer: D

Explanation

The Scrum Team is collectively responsible for its own dynamics and performance, including addressing conflicts that arise. While the hiring manager, Product Owner, and Scrum Master have important roles, the responsibility for the team's composition ultimately lies with the team itself.